Back Rasina District - Regional Water Supply Project
Identification details
Official title of the project Rasina District - Regional Water Supply Project
Website /
Region/City Rasina, Pomoravlje
Sector(s) Regional Water Supply System Improvement
Budget / EC contribution 13,950,000.00 €
Implementation period 01 March 2010 - 01 September 2011
Expected results The project implementation will provide healthy drinking water for over 250.000 inhabitants of the town of Kruševac and the municipalities of Aleksandrovac, Ćićevac, Varvarin and Trstenik, as well as the possibility to include parts of Paraćin and Ćuprija municipalities as well. Central regional drinking water treatment plant is located in Majdevo and raw water is supplied from the “Ćelije” reservoir on river Rasina.
Beneficiary Town of Kruševac and the municipalities of Aleksandrovac, Ćićevac, Varvarin, Trstenik, Paraćin and Ćuprija.
Partners EU, National Investment Plan, Water Directorate, Town of Kruševac and Municipality Ćićevac
Contact details
Summary
Summary of the project
(up to 1500 characters)
The project consists of the following components:
  • Rehabilitation and capacity improvement of the regional drinking water treatment plant in Majdevo settlement from 650 l/sec to 1000 l/sec;
  • Construction of “Lipovac” 5000 m3 capacity reservoir for balancing of water transfer supply towards Krusevac and other downstream consumers;
  • Finalization of the transmission mains towards Ćićevac and Varvarin together with a 4000 m3 reservoir in Varvarin;
  • Significant improvement of Kruševac distribution system by constructing the main distribution pipeline DN500;
  • Implementation of the remote supervision project and the regional water supply system management.
Main goal of the project
(up to 800 characters)
  1. To create preconditions for provision of adequate drinking water supply for additional 75.000 people (in total 250.000) in municipalities of Kruševac, Aleksandrovac, Varvarin, Ćićevac, Trstenik, Ćuprija and Paraćin;
  2. To ensure continuous fulfi lment of national and EU standards of drinking water supply;
  3. To ensure safe, constant and long-term drinking water supply in these municipalities by improving the capacity and technological process of the drinking water treatment plant;
  4. To transfer (supply) the necessary amounts of quality drinking water to the above mentioned municipalities, taking into consideration full control of working parameters of the system and its balanced and secure operation;
  5. To improve population health care in the above mentioned municipalities;
  6. To create preconditions for economic and social sustainable development in the region.
Specific objectives
(up to 800 characters)
  1. Rehabilitation and extension of the Water Treatment Plant (WTP) Component A / Amount: € 6.100.000
  2. Water supply transfer and upgrade of the water supply distribution Component B / Amount: € 6.900.000
  3. Transmission Line to Ćićevac Transmission Line to Varvarin plus Varvarin reservoir Distribution system O 500 Civil works reservoir Lipovac
  4. Other elements
  5. Component C / Amount: 950.000